BOE moves forward with capital financing plan

Published:

The Scottsboro Board of Education took a major step toward an extensive capital improvement plan Monday, October 6, beginning a financing process that could provide approximately $67 million for school construction and facility improvements.
During a called meeting on October 6, representatives presented the board with several financing scenarios designed around what the school system could reasonably afford in annual debt payments.

David Langham of The Frazer Lanier Company told board members that Scottsboro City Schools’ strong financial position could allow the board to borrow directly for the projects rather than relying on the City of Scottsboro to issue debt on its behalf, as has been done in the past.

Langham said changes in Alabama law now allow school boards to borrow directly, opening another avenue for the system as it prepares to undertake what could be one of its most significant facility investments in decades.

He praised the school system’s financial condition, telling board members that Scottsboro City Schools has maintained a strong cash position, balanced budgeting and positive financial performance.

The state requires school systems to maintain approximately one month of operating reserves, while Scottsboro currently has roughly four months, possibly slightly more, of cash on hand.

“You guys have done a fabulous job,” Langham told the board. “You have been extremely fiscally conservative and that has allowed you guys to build up a wonderful cash position as a board.”

He said that cash position, combined with balanced budgeting, favorable audits and growing revenues, should make Scottsboro City Schools a strong candidate in the bond market.

School officials worked with Frazer Lanier to determine an annual payment range the system could sustain while continuing to meet its other financial obligations.

That range was estimated between $2.2 million and $2.8 million annually.

Under the first scenario presented to the board, adding approximately $2.8 million to the system’s existing debt payments could generate slightly more than $56 million for capital projects.

At the lower $2.2 million annual payment level, the system could generate approximately $44 million.

Langham pointed out that the $600,000 difference in annual payments could translate into approximately $12 million more for projects.

The second scenario would involve refinancing debt associated with the system’s existing 2020B issue with the city.

By incorporating that debt into the new financing structure, the school system could potentially increase available project funding from approximately $56 million to $62 million at the higher annual payment level.

The third scenario goes even further.

Under that option, the school system would refinance the 2020B debt and increase its payments by approximately 3% every five years.

That structure could generate approximately $67 million at closing.

Langham said that scenario caught his attention because the school system’s identified capital “needs”, rather than wants, total somewhere in the low $70 million range.

The $67 million would also not necessarily represent the total amount ultimately available for construction.

Because all of the borrowed money would not be spent immediately, portions of the construction fund could be invested while architectural work, site preparation and construction progress.

Langham estimated those investment earnings could potentially bring total available funds into the neighborhood of $71 million to $72 million, depending on interest rates and the construction time line.

That could put the school system within reach of funding much of its identified needs.

“The projects you guys are going to tackle are going to set up this board to be able to welcome new students and educate those students for years and years and years to come,” Langham said.

Board of Education member Gary Speers questioned the wisdom of assuming revenues would continue increasing over the life of the debt, noting that revenue streams can rise or fall.

Langham acknowledged that future revenue cannot be guaranteed but described the proposed 3% payment increase every five years as conservative compared with financing structures used by other Alabama school systems.

He pointed to historical growth in sales and property tax collections and said the financing would include provisions allowing the board to refinance its debt in the future if circumstances warranted.

The proposed bonds are expected to have a 10-year redemption provision.

Langham explained that refinancing before that point could require funding the remaining interest through the 10th year, but restructuring could still be possible if revenues failed to grow as projected or if lower interest rates created an opportunity for savings.

The board is also preparing to enter the credit market as a first-time direct borrower.

Langham said the system’s cash reserves, revenue growth, management and financial history give him confidence Scottsboro City Schools could receive a rating within the “A” category.

“I fully believe you are going to be in the A category,” he told board members, adding that he believes the system may be able to make a strong argument for a rating near the A+ level.

A higher credit rating generally helps a borrower obtain more favorable interest rates.

The system is expected to seek ratings through Standard & Poor’s and Moody’s as part of the financing process.

If the process moves according to the preliminary schedule presented Monday, the financing could be completed before Christmas.
Documentation is expected to be prepared during October and submitted to rating agencies and the insurance company around October 26.
Meetings with rating agencies are anticipated during the weeks of November 9 or November 16.

The school system could receive its credit rating around December 1.

Closing is projected for approximately December 17.

At that point, the construction fund would be established and money could become available to begin paying project expenses.

Langham stressed that the board’s action Monday does not represent final approval of a $67 million borrowing package.

Instead, it begins the process.

The board will later receive the final financing proposal showing the actual interest rate, amount of money available and investment schedule before being asked to ratify the transaction.

Following the presentation, the board unanimously approved a resolution formally engaging The Frazer Lanier Company as investment banker and Bradley Arant Bolt & Cummings LLP as bond counsel for the proposed issuance of special tax school warrants.

Speers asked whether school officials had considered other firms before making the recommendation.

Superintendent Williams said another company had been considered and that she and the system’s financial staff felt confident moving forward with Frazer Lanier.

The board also authorized the superintendent to enter contract negotiations with Ward Scott Morris Architecture for architectural and design services related to the Capital Improvement Plan.

In another unanimous vote, the board authorized negotiations with Scout Program Management to manage the upcoming projects.

School officials said requests for proposals had been sent to seven companies seeking experienced K-12 construction project managers.

Five proposals were submitted and reviewed before Scout was recommended.

Superintendent Williams closed the meeting by describing the capital plan as an opportunity to shape Scottsboro City Schools for generations.
She noted that some school facilities date to 1966, while the building where the board was meeting has portions dating to 1928.
Williams said the district often uses the phrase “every student, every day,” but she wanted to add another element as the system moves into its next chapter.
“Every opportunity,” she said.
“That is what we are going to give the students of Scottsboro.”
Williams noted that facilities constructed through the upcoming plan will likely serve Scottsboro students for decades.
“We are going to be building facilities for students that have not even been born yet,” she said. “It’s something to be proud of.”
The board’s next work session and regular meeting are scheduled for November 5 at 4 p.m.